HAWORTH HALL
Project Highlights
Year Completed: 2019
Application: Education – University
Location: Lawrence, KS
Featured Product ~ Custom AHU
This project featured Air Enterprises SiteBilt custom air handling units. The customer replaced 3 old air handling units, which were in very tight quarters and didn’t have the door space to bring in a new air handling unit. Air Enterprises offered the SiteBilt custom air handling units which would be built right on site with pre-designed & built subassemblies. The subassemblies are made of lightweight aluminum, allowing for easy transport through doorways, hallways and elevators for simplified installation.
Did you know…
The project had a compressed schedule and the contractor only had (2) weeks to install the unit and ductwork. We were able to complete the project on schedule due to good coordination be-tween the contractor, sales staff & fabricator.
PROJECT TEAM
Contractor: McElroy’s
Engineer: Professional Engineering Consultants